PANEL FABRICATION SEQUENCES
|
# of | elapsd | total | elapsed |
Typical work sequence for most panels, | pers | hrs | hrs | days |
Varies some with size and complexity of details |
|
|
|
|
|
|
|
|
|
clean mold from previous use | 2 | 4 | 8 | 1 |
cut glass for first lamination | 2 | 2 | 4 |
|
prepare foam and fit to mold, radius cuts, edges tapered | 2 | 3 | 6 |
|
mask mold edges then apply release | 1 | 2 | 2 | 2 |
laminate 3x DB170 | 3 | 2 | 6 |
|
Apply foam core and vacuum bag entire mold | 3 | 1 | 3 |
|
remove vacuum materials after cure (minimum one day) | 2 | 1 | 2 |
|
contour and prepare for second lamination of 3 x DB 170 | 1 | 2 | 2 | 3 |
laminate 3x DB170 | 3 | 2 | 6 | 4 |
depending on details | 1 to 2 | 3 to 6 | up to 12 | 5 to 7 |
remove finished part and transport to storage area | 4 | 1 | 4 |
|
elapsed time, depending on curing temperatures this time of year, 7 working days |
|
|
|
7 |
|
|
|
|
|