PHASE ONE

Position as of October 2023

A link to the "FLOW CHART" (soon)

Completed when the boat CAN FLOAT!

Note: most of the listed segments will have their own pages and details of finishing details. Shop drawings and laminating schedules are being compiled while awaiting funding to carry on with the "real" work.

 

Tasks:     

complete Bows:  our current focus. 

The first pair of  STBD and PT sections are currently in the yard and close to finished. they  will be the "molds" for the second set. 

complete Sterns:                          

one is built needs "clean up" and duplicating

complete the Main Beam / mast support        in the design phase / most materials in stock 

complete Stbd hull:                   

nearly done, minor details and bulkheads to be installed, awaiting the installation of the bow

complete Pt hull:                          

nearly done, minor details and bulkheads to be installed, awaiting the installation of the bow

complete the Transom:

has been started and partly installed

complete Connection Beams:        completed and installed,

 

complete the Cabin:                    

most of the structural supports and many "roof panels" were completed (then lost some during IKE)

obtain and install electric propulsion system and storage batteries 

return to: THIS IS IT