PHASE ONE

Position as of September 2022

A link to the "FLOW CHART"

Completed when the boat CAN FLOAT!

Note: most of the listed segments will have their own pages and details of finishing details. Shop drawings and laminating schedules are being compiled while awaiting funding to carry on with the "real" work.

 

Tasks:     

complete Bows   details               our current focus.  The first pair of  STBD and PT sections are currently in the yard and close to finished.

                                                   they  will be the "molds" for the second set. 

complete Sterns                           one is built needs "clean up" and duplicating

complete the Main Beam / mast support        in the design phase / most materials in stock 

complete Stbd hull                      nearly done, minor details and bulkheads to be installed, awaiting the installation of the bow

complete Pt hull                           nearly done, minor details and bulkheads to be installed, awaiting the installation of the bow

complete the Transom                  has been started and partly installed

complete Connection Beams        completed and installed,

Install lower close out then floatation between upper deck  and lower close out, (between the hulls), install upper deck.

complete the Cabin                      most of the structural supports and many "roof panels" were completed (then lost some during IKE)

obtain and install electric propulsion system and storage batteries 